Bid Publish Date
31-Aug-2026, 6:44 pm
Bid End Date
14-Sep-2026, 7:00 pm
EMD
₹22,500
Value
₹17,96,487
Location
Progress
Western Coalfields Limited (Coal India Limited) invites bids for the erection of a 4 km 3.3 KV overhead line to supply power to the Upcoming Quarry 2 Project from an existing 11 KV by 3.3 KV substation at Bhatadi OCM, Chandrapur Area. Estimated value is ₹1,796,487.00 with an EMD of ₹22,500. The contract allows a quantity/duration adjustment up to 25%. Completion target is 60 days from commencement; site handover starts within 10 days of award. Bid validity is 120 days. Payment on running bills will be 95% of work value. Security deposits consist of 5% performance security and 5% retention. Bidders must inspect site before quoting and ensure DD-based EMD delivery to the specified SBI account.
Project type: erection of overhead line
Length/scope: 4 km 3.3 KV line to supply quarry power
Source: from 11 KV to 3.3 KV substation at Bhatadi OCM
Delivery window: 60 days from commencement; site handover on award day
Payment: 95% running bills; EMD ₹22,500; 5% performance/security deposits
Bid validity: 120 days; EMD online or via DD; DD in favor of WCL with SBI Chandrapur details
Security: 5% Performance + 5% Retention; LOA-based submission within 21 days
Delivery: 60 days from site handover; site inspection before quoting; taxes included
Running bills paid at 95% of work value; final payment per contract; GST clearly indicated in quotes
60 days from the date of commencement; commencement counted from 10th day of award or handover of site
Not specified in provided data; standard GeM terms may apply
Experience in similar 3.3 KV/low-voltage line erection works
Financial capacity to sustain 60-day project with progress payments
GST registration and PAN, plus relevant safety and electrical contractor licenses
Quantity
1
Similar Category
Operation And Maintenance Of Electro-Mechanical Installations
Bid Type
Two Packet Bid
Bid Validity
120 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Tech Clarification Time
7 Days
EMD Required
Yes
MII Compliance
Yes
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Min. Avg. Annual Turnover
6
Experience Required
7 Year (s)
Arbitration Clause
No
Mediation Clause
No
Tender Category
Service
Bid To RA
No
Bid To RA Enabled
No
Item Category
Custom Bid for Services - Work for Erection of 4 km of 3point3 KV OH line for catering power supply to Upcoming Quarry 2 Project from existing 11 KV by 3point3 KV Substation at Bhatadi OCM of Chandrapur Area WCL as per scope of work and schedule of w..
Advisory Bank
ICICI
ePBG Percentage
5%
ePBG Duration (Months)
4
Payment Timelines
Payments shall be made to the Seller within 45 days of issue of service delivery acceptance certificate (SDAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Delivery Locations
1
Delivery Cities
Chandrapur
Delivery Pincodes
442403
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Pramod Kumar Dhadse | 442403,Regional Stores, WCL, Durgapur Opencast, P.O. DURGAPUR Distt Chandrapur, ( M.S)Pin 442 403 | Chandrapur | Maharashtra | 442403 | Project / Lumpsum Based | - | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
OTHER
OTHER
OTHER
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
GEM_GENERAL_TERMS_AND_CONDITIONS
Discover companies most likely to bid on this tender
GST registration certificate
Permanent Account Number (PAN) card
Experience certificates for similar 3.3 KV/low-voltage line erection works
Financial statements or net worth proof
EMD submission proof (online GeM receipt or scanned DD proof)
Technical bid documents and any OEM authorizations
Site inspection report (if available) and safety compliance certificates
Any certificates requested in bid document/ATC/Corrigendum
Key insights about MAHARASHTRA tender market
To bid, submit online through GeM with EMD ₹22,500 and provide all requested certificates; ensure site inspection prior to quoting; include 95% running bill payment terms and 60-day completion timeline from award handover.
Required documents include GST certificate, PAN, experience certificates for similar work, financial statements, EMD proof (GeM receipt or DD), technical bid, OEM authorizations, and safety/compliance certificates; ensure submission per ATC.
Bidders should expect payment on running bills at 95% of work value; final settlement per contract; the EMD and security deposits follow a 5% performance and 5% retention structure; GST must be indicated in all quotes.
The contract requires completion within 60 days from commencement; commencement counted from award handover or site handover; delays may impact penalties under GeM terms if applicable.
EMD is ₹22,500; bidders may submit online via GeM or provide a DD payable to WCL WARDHA VALLEY AREA at SBI Chandrapur; hard copies must reach within 5 days post bid end date.
Yes, an option clause up to 25% allows the buyer to increase contract quantity or duration at issue time; post-issue up to 25% with service provider consent for lumpsum works.
Bidders should inspect actual job conditions at site; ensure that rates account for site-specific factors, safety requirements, and the need to integrate with the existing 11 kV to 3.3 kV substation near Bhatadi OCM.
While explicit standards are not listed, bidders should comply with standard electrical erection practices and safety norms; ensure all certificates and documents requested in the bid and ATC are submitted with the proposal.