Progress
Organization: Indian Council Of Agricultural Research (ICAR) under the Department Of Agricultural Research And Education (DARE). Location: Junagadh, Gujarat 362001. Procurement: Aluminium partitioning of the laboratory. Quantity/Value: No BOQ items listed; overall value not disclosed. Delivery terms: Option to increase quantity up to 25% at contracted rates; delivery period starts from the last date of original order. Unique clause: Delivery time adjusts with option quantity using the formula (Additional quantity ÷ Original quantity) × Original delivery period, with a minimum of 30 days. This tender requires bidders to adhere to the option clause and related delivery calculations.
Product/service names: aluminium laboratory partitioning system
Quantity/capacity: not disclosed in BOQ; scope-based procurement
EMD/estimated value: not specified; option for 25% quantity change
Experience: prior similar lab partitioning experience preferred
Quality/standards: compliance with internal ICAR AtC; IS/IS-labeled certifications not specified
Delivery/Installation: delivery timeline linked to original order date; extended time rules apply
Warranty/Support: not specified in provided data
Delivery extension governed by option clause with 30-day minimum
FDR-based security acceptable in lieu of PBG with timely submission
Mandatory compliance sheet and non-blacklist certificate
EMD alternative via FDR in favor of ICAR-IIGR Junagadh; original FDR delivery within 15 days of award; scanned copy upload required.
Delivery period starts from last date of original delivery order; additional time for increased quantity calculated by (additional/original) × original days, minimum 30 days.
Not specified in provided terms; standard GeM/ICAR procurement penalties may apply per contract.
Experience in aluminium partitioning or related laboratory fit-out
Ability to submit FDR-based security as alternative to PBG
Compliance with vendor ATC and non-blacklist requirements
Quantity
2650
Bid Type
Two Packet Bid
Bid Validity
180 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
Aluminium partitioning of the laboratory
Advisory Bank
State Bank of India
ePBG Percentage
3%
ePBG Duration (Months)
6
Max Delivery Days
15
Delivery Locations
1
Delivery Cities
Junagadh
Delivery Pincodes
362001
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Mohd Saif | 362001,ICAR-Indian Institute of Groundnut Research, PB No-5, Ivnagar Road, Junagadh, Gujarat-362001 | Junagadh | Gujarat | 362001 | 2650 | 15 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
Discover companies most likely to bid on this tender
GST registration certificate
Permanent Account Number (PAN)
Experience certificates for similar aluminium partitioning works
Financial statements (latest financials)
EMD/Security deposit documentation or FDR (as applicable)
Technical bid documents and compliance sheets
OEM authorizations or vendor certifications (if applicable)
Non-blacklist certificate
Key insights about GUJARAT tender market
Bidders must submit GST, PAN, experience certificates, financials, EMD or FDR-based security, technical compliance, and OEM authorizations. Upload a compliance sheet for specs, non-blacklist certificate, and brochure alignments. Delivery terms allow up to 25% quantity variation with calculated extension days and a minimum 30 days.
Required documents include GST registration, PAN, latest financial statements, previous project experience certificates for lab partitioning, EMD proof or FDR security, technical bid documents, OEM authorizations, and a non-blacklist certificate. Upload scanned copies and provide original FDR within 15 days of award.
Delivery begins from the last date of the original delivery order. If quantity increases by up to 25%, extended time is calculated as (additional quantity/original quantity) × original delivery period, with a minimum of 30 days; extensions may continue up to the original period.
Security can be provided as a Fixed Deposit Receipt (FDR) in the name of Director, ICAR-IIGR, Junagadh A/C (Seller). The FDR must be withdrawable on demand and must be uploaded and followed by delivering the original FDR within 15 days after award.
Submit a compliance sheet accepting specs, non-blacklist certificate, and any brochure or offered material aligned to bid specs. Ensure all documents are uploaded in the bid as per Bid ATC; maintains alignment with ICAR procurement terms.
No explicit standards like IS or ISO are listed in the provided data. Bidders should rely on ICAR ATC requirements and supplier certifications, ensuring the supplied aluminium partitioning meets internal ICAR-DARE quality expectations and aligns with non-blacklist criteria.
Prepare to supply up to 25% more quantity at contracted rates. Plan for delivery time extension using the formula: (Additional quantity ÷ Original quantity) × Original delivery period, with a minimum extension of 30 days.
Prove prior experience in similar lab fit-outs, provide financial stability documentation, include OEM authorizations if applicable, and ensure compliance with non-blacklist status. Also ensure ability to provide FDR-based security if requested by ICAR.