TenderDekho Logo
Active GEM

Hindustan Petroleum Corporation Ltd Pune DG Electrical & Instrumentation Tender 2026 EMD ₹105000

Bid Publish Date

08-Sep-2026, 7:20 pm

Bid End Date

18-Sep-2026, 8:00 pm

EMD

₹1,05,000

Progress

Issue08-Sep-2026, 7:20 pm
AwardPending

Key Highlights

  • HPCL Pune procurement governing electrical testing, calibration, cabling and safety equipment
  • EMD amount of ₹105,000—critical bid security requirement
  • Option clause enabling ±25% quantity variation at contracted rates
  • Delivery period mechanics: base and extended periods with minimum 30 days

Tender Overview

Hindustan Petroleum Corporation Ltd (HPCL) invites bids for a wide range of electrical and instrumentation services and works at its Pune, Maharashtra facility (PIN 410301). The procurement scope spans DG STACK sampling arrangements, transformer testing and calibration, thermography, insulation testing, cable laying, switchgear components, meters and related testing/repair activities. The tender references 70 BOQ items and an EMD of ₹105,000. A notable differentiator is the option clause allowing quantity variation up to 25% of bid quantity, with a calculated extension rule. Bidders should be aware of the bulk nature of works and the need to align with HPCL’s commissioning timeline across multiple sub-works.

Technical Specifications & Requirements

  • 70 items in the BOQ indicating a broad spectrum of electrical and instrumentation services (calibration, testing, repair, laying and safety equipment).
  • EMD: ₹105,000 ensures bid security and compliance with procurement norms.
  • Option clause permits up to 25% increase/decrease in ordered quantity at contracted rates.
  • Delivery/extension mechanics: delivery period begins from the last date of the original delivery order; additional time formula is (Increased quantity ÷ Original quantity) × Original delivery period with a minimum of 30 days.
  • HPCL has uploaded an ATC/Bid terms document and includes a complex scope spread across multiple sub-works; bidders must review terms for compliance and risk management.
  • No product-specific technical specifications are listed in the provided extract; bidders should verify BOQ items and cross-check against site requirements.

Terms, Conditions & Eligibility

  • EMD: ₹105,000 against bid submission.
  • Option Clause: quantity may change up to 25% during contract; delivery period adjustments follow a defined formula with a minimum of 30 days.
  • Delivery timeline: defined as per original/extended delivery orders; bidders must align with HPCL scheduling.
  • An official ATC document has been uploaded; bidders should review for compliance, documentation and risk assessment.
  • Do not rely on generic commitments; ensure all 70 BOQ items, safety certifications and site-specific requirements are addressed in the bid.

Key Specifications

  • Product/service names: electrical testing, calibration, insulation testing, meter testing, transformer oil testing and related calibration works

  • Quantities/scale: 70 items in BOQ (no item-wise quantities specified in extract)

  • EMD amount: ₹105,000

  • Experience/eligibility: not explicitly stated; bidders should provide relevant experience certificates

  • Quality/compliance: ATC document uploaded; verify safety and regulatory compliance

Terms & Conditions

  • 25% quantity variation right within contract period

  • Delivery period starts from last date of original order

  • Minimum 30 days extension if option clause exercised

Important Clauses

Payment Terms

Not specified in extract; bidders should review ATC for payment milestones and terms

Delivery Schedule

Delivery period governed by original and extended delivery orders with 30-day minimum extension rule

Penalties/Liquidated Damages

Not specified in extract; refer to ATC for LD provisions and performance criteria

Bidder Eligibility

  • Must meet EMD submission of ₹105,000

  • Provide experience certificates for similar electrical/instrumentation works

  • Submit GST, PAN, and financial statements

  • Adhere to HPCL ATC terms and 25% quantity variation clause

Tender Data

Bid Details

Quantity

5053

Category

DG STACK sampling arrangement SV-11 SV-13 and SV-08

Bid Type

Two Packet Bid

Bid Validity

120 (Days)

Bid Type

Service

Evaluation

Total value wise evaluation

Inspection Required

No

Tech Clarification Time

2 Days

Preference & Exemptions

EMD Required

Yes

MII Purchase Preference

Yes

MII Preference Band

L1+20%

MSE Purchase Preference

Yes

MSE Preference Band

L1+15%

MSE Exemption/Relaxation

No

Startup Exemption/Relaxation

No

Bid Splitting Applied

No

Requirements

Arbitration Clause

No

Mediation Clause

No

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

No

Item Category

DG STACK sampling arrangement SV-11 SV-13 and SV-08 , HT Technician Arrangement for Transformer LA works , Thermography at Chakan Spread , Volt meter Ammeter and Energy meter testing calibration at Chakan , Transformer oil filtration Chakan , Transformer oil Testing Chakan , Multimeter Calibration , Tong tester, Lux level meter, Thermography meter calibration , GOD of 2-pole structure servicing and painting , TT PT GD RTD Testing and Calibration , APFC panel Testing and Repairing , Insulation MAT Testing HT and LT , Earth Tester Calibration with Certificate , Megger Calibration with Certificate , Battery Discharge Testing C10 or C5 , PF Panel controller , SUP AND LAYING 2.5 SQ MM 4 CORE COPPER ARM CABLE , SUP AND LAYING 25 SQ MM 1 CORE Aluminium ARM CABLE , SLD PANEL AND EARTH PITS DRAWINGS , 25 multiply 3 GI STRIP , 50 multiply 6 GI STRIP , Laying 25 multiply 3 GI STRIP , Laying 50 multiply 6 GI STRIP , 6 SQ MM multiply 1 C GREEN WIRE , 4 SQ MM multiply 1 C GREEN WIRE , HT GLOVES 22KV with Proper Certificate , HT GLOVES 6.6KV with Proper Certificate , LT GLOVES 440V with Proper Certificate , PVC HANDGLOVES , 19 MM DC GLAND FLP , 20 MM DC GLAND FLP , 25 MM DC GLAND FLP , 19 MM DUMMY PLUG FLP , 20 MM DUMMY PLUG FLP , 25 MM DUMMY PLUG FLP , 120 WATT FLP LIGHT with proper certificate , 200 WATT FLP LIGHT with proper certificate , HRC FUSE 2 AMP , HRC FUSE 4 AMP , HRC FUSE 10 AMP , HRC FUSE 16 AMP , HRC FUSE 32 AMP , HRC FUSE 63 AMP , HRC FUSE DOUBLE 110EET BUSSMANN FOR UPS , 56 ET ETN BUSSMANN FUSE UPS , STREET Light 120 Watt , FLOOD Light 150 Watt , SS NUT BOLT 6 multiply 25 MM WITH DOUBLE WASHER , SS NUT BOLT 8 multiply 25 MM WITH DOUBLE WASHER , LT MAT , HT MAT 22 KV , HT MAT 6.6 KV , TUBE Light 22 WATT , WD 40 500 ML , CRC 200 ML , FOAM SPRAY , DISTILLED WATER , FLP TORCH , FLP EXHAUST FAN , FLP EXHAUST FAN REPAIRING , AC PCB CARD , Silica Gel Supply , DANGER BOARDS 22 KV , DANGER BOARDS 6.6 KV , DANGER BOARDS 415 V , MCB 2P 6 AMP , MCB 2P 16 AMP , ELCB 4P 25 AMP , ELCB 4P 32 AMP , BATTERY FOR DG 180 AH, 12V on Buyback Basis

Advisory Bank

ICICI

Payment Timelines

Payments shall be made to the Seller within 30 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)

Delivery Details

Max Delivery Days

730

Delivery Locations

1

Delivery Cities

Pune

Delivery Pincodes

410501

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
Pritish Kumar Basumatary410501,Hindustan Petroleum Corporation Limited UCSPL Chakan, Pune Mahalunge Ingle, MaharashtraPuneMaharashtra4105013730-

Authority Records

MINISTRY OF PETROLEUM AND NATURAL GASHINDUSTAN PETROLEUM CORPORATION LTD

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 5

GeM-Bidding-9865936.pdf

Main Document

BOQ Document

BOQ

BOQ Document

BOQ

Other Documents

OTHER

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Authority & Contact

Department

NA

Office Name

Petroleum House

Grievance Contact

[email protected]

Bill of Quantities (BOQ) 70 Items Sign in for GEM prices

#1

DG STACK sampling arrangement SV-11 SV-13 and SV-08

Pls refer tender terms and condition for detailed description.

3 eac Delivery: 730 days
#2

HT Technician Arrangement for Transformer LA works

Pls refer tender terms and condition for detailed description.

8 eac Delivery: 730 days
#3

Thermography at Chakan Spread

Pls refer tender terms and condition for detailed description.

4 eac Delivery: 730 days
#4

Volt meter Ammeter and Energy meter testing calibration at Chakan

Pls refer tender terms and condition for detailed description.

2 eac Delivery: 730 days
#5

Transformer oil filtration Chakan

Pls refer tender terms and condition for detailed description.

4 eac Delivery: 730 days
#6

Transformer oil Testing Chakan

Pls refer tender terms and condition for detailed description.

2 eac Delivery: 730 days
#7

Multimeter Calibration

Pls refer tender terms and condition for detailed description.

2 eac Delivery: 730 days
#8

Tong tester, Lux level meter, Thermography meter calibration

Pls refer tender terms and condition for detailed description.

2 eac Delivery: 730 days
#9

GOD of 2-pole structure servicing and painting

Pls refer tender terms and condition for detailed description.

12 eac Delivery: 730 days
#10

TT PT GD RTD Testing and Calibration

Pls refer tender terms and condition for detailed description.

2 eac Delivery: 730 days
#11

APFC panel Testing and Repairing

Pls refer tender terms and condition for detailed description.

4 eac Delivery: 730 days
#12

Insulation MAT Testing HT and LT

Pls refer tender terms and condition for detailed description.

2 eac Delivery: 730 days
#13

Earth Tester Calibration with Certificate

Pls refer tender terms and condition for detailed description.

2 eac Delivery: 730 days
#14

Megger Calibration with Certificate

Pls refer tender terms and condition for detailed description.

2 eac Delivery: 730 days
#15

Battery Discharge Testing C10 or C5

Pls refer tender terms and condition for detailed description.

1 eac Delivery: 730 days
#16

PF Panel controller

Pls refer tender terms and condition for detailed description.

3 eac Delivery: 730 days
#17

SUP AND LAYING 2.5 SQ MM 4 CORE COPPER ARM CABLE

Pls refer tender terms and condition for detailed description.

500 mr Delivery: 730 days
#18

SUP AND LAYING 25 SQ MM 1 CORE Aluminium ARM CABLE

Pls refer tender terms and condition for detailed description.

100 m Delivery: 730 days
#19

SLD PANEL AND EARTH PITS DRAWINGS

Pls refer tender terms and condition for detailed description.

40 eac Delivery: 730 days
#20

25 multiply 3 GI STRIP

Pls refer tender terms and condition for detailed description.

400 mr Delivery: 730 days
#21

50 multiply 6 GI STRIP

Pls refer tender terms and condition for detailed description.

200 m Delivery: 730 days
#22

Laying 25 multiply 3 GI STRIP

Pls refer tender terms and condition for detailed description.

400 m Delivery: 730 days
#23

Laying 50 multiply 6 GI STRIP

Pls refer tender terms and condition for detailed description.

200 m Delivery: 730 days
#24

6 SQ MM multiply 1 C GREEN WIRE

Pls refer tender terms and condition for detailed description.

200 mr Delivery: 730 days
#25

4 SQ MM multiply 1 C GREEN WIRE

Pls refer tender terms and condition for detailed description.

200 m Delivery: 730 days
#26

HT GLOVES 22KV with Proper Certificate

Pls refer tender terms and condition for detailed description.

2 eac Delivery: 730 days
#27

HT GLOVES 6.6KV with Proper Certificate

Pls refer tender terms and condition for detailed description.

4 eac Delivery: 730 days
#28

LT GLOVES 440V with Proper Certificate

Pls refer tender terms and condition for detailed description.

6 eac Delivery: 730 days
#29

PVC HANDGLOVES

Pls refer tender terms and condition for detailed description.

15 paa Delivery: 730 days
#30

19 MM DC GLAND FLP

Pls refer tender terms and condition for detailed description.

60 eac Delivery: 730 days
#31

20 MM DC GLAND FLP

Pls refer tender terms and condition for detailed description.

60 eac Delivery: 730 days
#32

25 MM DC GLAND FLP

Pls refer tender terms and condition for detailed description.

30 eac Delivery: 730 days
#33

19 MM DUMMY PLUG FLP

Pls refer tender terms and condition for detailed description.

30 eac Delivery: 730 days
#34

20 MM DUMMY PLUG FLP

Pls refer tender terms and condition for detailed description.

30 eac Delivery: 730 days
#35

25 MM DUMMY PLUG FLP

Pls refer tender terms and condition for detailed description.

30 eac Delivery: 730 days
#36

120 WATT FLP LIGHT with proper certificate

Pls refer tender terms and condition for detailed description.

36 eac Delivery: 730 days
#37

200 WATT FLP LIGHT with proper certificate

Pls refer tender terms and condition for detailed description.

36 eac Delivery: 730 days
#38

HRC FUSE 2 AMP

Pls refer tender terms and condition for detailed description.

60 eac Delivery: 730 days
#39

HRC FUSE 4 AMP

Pls refer tender terms and condition for detailed description.

60 eac Delivery: 730 days
#40

HRC FUSE 10 AMP

Pls refer tender terms and condition for detailed description.

60 eac Delivery: 730 days
#41

HRC FUSE 16 AMP

Pls refer tender terms and condition for detailed description.

60 eac Delivery: 730 days
#42

HRC FUSE 32 AMP

Pls refer tender terms and condition for detailed description.

60 eac Delivery: 730 days
#43

HRC FUSE 63 AMP

Pls refer tender terms and condition for detailed description.

60 eac Delivery: 730 days
#44

HRC FUSE DOUBLE 110EET BUSSMANN FOR UPS

Pls refer tender terms and condition for detailed description.

12 eac Delivery: 730 days
#45

56 ET ETN BUSSMANN FUSE UPS

Pls refer tender terms and condition for detailed description.

12 eac Delivery: 730 days
#46

STREET Light 120 Watt

Pls refer tender terms and condition for detailed description.

36 eac Delivery: 730 days
#47

FLOOD Light 150 Watt

Pls refer tender terms and condition for detailed description.

36 eac Delivery: 730 days
#48

SS NUT BOLT 6 multiply 25 MM WITH DOUBLE WASHER

Pls refer tender terms and condition for detailed description.

200 eac Delivery: 730 days
#49

SS NUT BOLT 8 multiply 25 MM WITH DOUBLE WASHER

Pls refer tender terms and condition for detailed description.

200 eac Delivery: 730 days
#50

LT MAT

Pls refer tender terms and condition for detailed description.

200 m2 Delivery: 730 days
#51

HT MAT 22 KV

Pls refer tender terms and condition for detailed description.

50 m2 Delivery: 730 days
#52

HT MAT 6.6 KV

Pls refer tender terms and condition for detailed description.

75 m2 Delivery: 730 days
#53

TUBE Light 22 WATT

Pls refer tender terms and condition for detailed description.

20 eac Delivery: 730 days
#54

WD 40 500 ML

Pls refer tender terms and condition for detailed description.

18 eac Delivery: 730 days
#55

CRC 200 ML

Pls refer tender terms and condition for detailed description.

18 eac Delivery: 730 days
#56

FOAM SPRAY

Pls refer tender terms and condition for detailed description.

24 eac Delivery: 730 days
#57

DISTILLED WATER

Pls refer tender terms and condition for detailed description.

1,000 l Delivery: 730 days
#58

FLP TORCH

Pls refer tender terms and condition for detailed description.

8 eac Delivery: 730 days
#59

FLP EXHAUST FAN

Pls refer tender terms and condition for detailed description.

2 eac Delivery: 730 days
#60

FLP EXHAUST FAN REPAIRING

Pls refer tender terms and condition for detailed description.

4 eac Delivery: 730 days
#61

AC PCB CARD

Pls refer tender terms and condition for detailed description.

10 eac Delivery: 730 days
#62

Silica Gel Supply

Pls refer tender terms and condition for detailed description.

15 kg Delivery: 730 days
#63

DANGER BOARDS 22 KV

Pls refer tender terms and condition for detailed description.

20 eac Delivery: 730 days
#64

DANGER BOARDS 6.6 KV

Pls refer tender terms and condition for detailed description.

12 eac Delivery: 730 days
#65

DANGER BOARDS 415 V

Pls refer tender terms and condition for detailed description.

60 eac Delivery: 730 days
#66

MCB 2P 6 AMP

Pls refer tender terms and condition for detailed description.

6 eac Delivery: 730 days
#67

MCB 2P 16 AMP

Pls refer tender terms and condition for detailed description.

6 eac Delivery: 730 days
#68

ELCB 4P 25 AMP

Pls refer tender terms and condition for detailed description.

6 eac Delivery: 730 days
#69

ELCB 4P 32 AMP

Pls refer tender terms and condition for detailed description.

6 eac Delivery: 730 days
#70

BATTERY FOR DG 180 AH, 12V on Buyback Basis

Pls refer tender terms and condition for detailed description.

3 eac Delivery: 730 days

Categories 86

🤖 AI-Powered Bidder Prediction

Discover companies most likely to bid on this tender

Live AI
Historical Data

Required Documents

1

GST registration certificate

2

Permanent Account Number (PAN) card

3

Experience certificates of similar electrical/instrumentation projects

4

Financial statements (audited if available)

5

EMD/payment proof of ₹105,000

6

Technical bid documents and compliance certificates

7

OEM authorizations (if applicable) and calibration/test certificates

8

Any site-specific safety and quality certifications

Frequently Asked Questions

Key insights about MAHARASHTRA tender market

How to bid for HPCL Pune electrical testing tender 2026?

Bidders should submit the EMD of ₹105,000 along with GST, PAN, experience certificates and financial statements. Review the ATC document, confirm 70 BOQ items, and ensure compliance with the 25% quantity variation clause. Prepare OEM authorizations if required and ensure site safety certifications are up to date.

What documents are required for HPCL Pune bid submission 2026?

Required documents include GST registration, PAN, audited financial statements, experience certificates in similar works, EMD proof of ₹105,000, technical bid and calibration certificates, OEM authorizations, and safety/quality certifications. Also ensure ATC compliance documents are attached.

What are the delivery requirements for HPCL Pune tender 2026?

Delivery is governed by the original delivery order with possible extension; the period for additional time is calculated as (Increased quantity ÷ Original quantity) × Original delivery period, with a minimum of 30 days. Ensure scheduling aligns with site conditions and HPCL rollout plans.

What is the EMD amount for the HPCL Pune procurement 2026?

The required bid security is ₹105,000. Provide payment proof via online transfer or as DD demand draft per HPCL terms; ensure the EMD remains valid through bid evaluation and contract award.

What standards or ATC documents are referenced in HPCL Pune bid 2026?

An ATC document has been uploaded by HPCL; bidders must review it for compliance with calibration, testing, safety and equipment standards. Align bid with the ATC requirements to avoid disqualification and ensure proper documentation.

How many items are included in the HPCL Pune BOQ 2026 tender?

The BOQ comprises 70 items covering sampling, testing, calibration, wiring, and associated components. Verify item-wise scope in the BOQ and prepare separate technical proposals for each category to ensure comprehensive coverage.

What is the location for HPCL tender 2026 and what scope does it cover?

Tender location is Pune, Maharashtra 410301. The scope includes DG STACK sampling arrangements, transformer testing, thermography, meters testing/calibration, insulation and wiring works, and related repair/maintenance activities across multiple sub-works.

What is the eligibility criteria for HPCL Pune electrical works tender 2026?

Eligibility requires submission of EMD ₹105,000, GST and PAN, evidence of relevant past projects, financial statements, and calibration/technical certifications. Bidders should also provide OEM authorizations if required and comply with the ATC terms and the 25% variation clause.