Bid Publish Date
04-Sep-2026, 4:56 pm
Bid End Date
14-Sep-2026, 5:00 pm
Location
Progress
Bharat Electronics Limited (bel), under the Department Of Defence Production, invites bids for the Boom Barrier category to be supplied, installed, tested, and commissioned at BEL Kotdwar in Pauri Garhwal, Uttarakhand 246001. The contract covers Supply, Installation, Testing and Commissioning with a delivery window of 45 days from order release. The successful bidder must provide OEM warranty certificates and ensure on-site installation and training. The ATC clause allows up to 25% quantity variation, at contracted rates, during or after order placement. Payment is 100% within 30 days after receipt and successful installation; LD of 0.5% per day may apply for delays. Installation and commissioning are required at BEL Kotdwar premises, with post-installation support from a domestic service network.
Boom barrier scope: supply, installation, testing, commissioning
Delivery within 45 days from order release
Warranty: 1 year from final acceptance; OEM certificates with delivery
Installation site: BEL Kotdwara premises, Uttarakhand
Variation clause: +/-25% quantity at contracted rates during contract validity
Payment: 100% via RTGS/NEFT within 30 days after receipt and installation
Penalties: LD at 0.5% per day for delays
Service network: domestic post-sales support centers
Delivery within 45 days; LD up to 0.5% daily
100% payment within 30 days after installation
Quantity variation up to 25% at contracted rates
100% payment via RTGS/NEFT within 30 days after receipt of material and successful installation at BEL Kotdwara.
Supply, installation and testing to be completed within 45 days from order release date.
Late delivery may incur liquidated damages at 0.5% of contract value per day, subject to contractual terms.
Demonstrated capability to install and commission boom barrier systems at BEL Kotdwara
Nationwide service center presence or ability to establish within India
Compliance with OEM warranty provisions and to supply OEM certificates at delivery
Quantity
3
Bid Type
Two Packet Bid
Bid Validity
30 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Past Performance
50 %
Warranty Period
1 years
Experience Required
3 Year (s)
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
BOOM BARRIER
Advisory Bank
State Bank of India
ePBG Percentage
5%
ePBG Duration (Months)
15
Payment Timelines
Payments shall be made to the Seller within 30 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
3
Delivery Locations
1
Delivery Cities
Pauri Garhwal
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| - | Pauri Garhwal | Pauri Garhwal | - | - | - | 3 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
Discover companies most likely to bid on this tender
GST registration certificate
Permanent Account Number (PAN) card
Experience certificates of similar Boom barrier supply/installations
Financial statements (last 2-3 years)
EMD documents (if applicable, as per tender terms)
Technical bid documents demonstrating installation capability
OEM authorization / dealership certificate
Quality/warranty certificates from OEM
Service center network details near consignee locations
Key insights about UTTARAKHAND tender market
Bidders must submit OEM authorization, GST, PAN, experience certificates, financial statements, and technical bid documents. Ensure installation capability at BEL Kotdwara, provide service network details, and confirm OEM warranty certificates. Delivery within 45 days and 100% payment within 30 days after acceptance are key terms.
Required documents include GST certificate, PAN, experience certificates for similar installations, financial statements, OEM authorization, technical bid, service center details, and OEM warranty certificates. Also include any applicable EMD documentation as per terms.
Delivery must be completed within 45 days from order release. Payment is 100% through RTGS/NEFT within 30 days after receipt and successful installation at BEL Kotdwara premises.
A 1-year warranty from final acceptance or after installation, with OEM warranty certificates provided at delivery. Service network coverage in INDIA is required for post-sale support.
Yes, up to ±25% variation in quantity at contracted rates during the contract period or at the time of placing the order, with delivery time adjusted accordingly.
Late delivery triggers liquidated damages at 0.5% per day of the contract value, up to the stipulated contractual limit, ensuring timely delivery and payment settlement.
Installation and commissioning must be performed at BEL Kotdwara premises in Uttarakhand, with on-site training and troubleshooting included in scope.
Scope includes supply, installation, testing, and commissioning of the boom barrier and associated accessories, with end-to-end delivery and site acceptance testing.